The materials manager for a billiard ball maker must periodically place orders for resin,one of the raw materials used in producing billiard balls.She knows that manufacturing uses resin at a rate of 50 kilograms each day,and that it costs $.04 per day to hold a kilogram of resin in inventory.She also knows that the order costs for resin are $100 per order,and that the lead time for delivery is four (4) days. If order size was 1,000 kilograms of resin,what would be the length of an order cycle?
A) 0.05 days
B) 4 days
C) 16 days
D) 20 days
E) 50 days
Correct Answer:
Verified
Q116: The need for safety stock can be
Q117: What is not required for distribution requirement
Q118: Which one of the following is implied
Q119: Which of these products would be most
Q120: Distribution requirements planning (DRP)is a planning method
Q122: The manager of the Quick Stop Corner
Q123: The manager of the Quick Stop Corner
Q124: The Operations Manager for Shadyside Savings &
Q125: The time interval between ordering and receiving
Q126: Ann Chovies,owner of the Perfect Pasta Pizza
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents