The maker of the world-famous Widget needs to design a product layout for a new product,the amazing "Thatsit".The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a "Thatsit". For output to equal projected demand,what should be the actual cycle time for this production line?
A) 54 seconds
B) 27 seconds
C) 20 seconds
D) 18 seconds
E) 14 seconds
Correct Answer:
Verified
Q127: For line balancing,cycle time is computed as:
A)daily
Q128: A company is designing a product layout
Q129: Using the method developed by Richard Muther,which
Q130: QRS Corp.is designing a product layout for
Q131: The maker of the world-famous Widget needs
Q133: QRS Corp.is designing a product layout for
Q134: A company is designing a product layout
Q135: QRS Corp.is designing a product layout for
Q136: Using the method developed by Richard Muther,which
Q137: The maker of the world-famous Widget needs
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents