The plant manager for the local electric utility company wants to know the reliability of one of his small hydroelectric power generating systems.This system is comprised of two components: a generator which has a random failure rate of one in every two years of operation; and a transformer which has a random failure rate of one in every five years of operation.If he were to add just a backup generator,with the same failure rate,what would be the probability that this system would perform reliably for a period of one year?
A) 0.48
B) 0.60
C) 0.72
D) 0.75
E) 0.96
Correct Answer:
Verified
Q34: The chief of the design team for
Q35: The Readylite Company produces a flashlight which
Q36: The plant manager for the local electric
Q37: The chief of the design team for
Q38: The Readylite Company produces a flashlight which
Q40: The chief design engineer for Colonial Warning
Q41: A computer has three main modules which
Q42: Usually,a number of products or parts fail
Q43: A certain product is comprised of two
Q44: An air purification system is expected to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents