Hemo-tech, Inc., a biomedical technology and research laboratory, produces a standard blood filtering device on an assembly line basis. Six basic tasks are performed along an assembly line. The time to perform each task and the tasks that must immediately precede each task are in the table below. Twenty pumps per 450-minute day must be produced by the assembly line.
a. Draw the network diagram of the precedence relationships.
b. Identify the absolute minimum and maximum cycle times.
c. How many workstations are required to meet the schedule?
d. What is the cycle time required to meet demand?
e. Balance this line using most following tasks heuristic.
f. What is the efficiency of the line obtained in part e?
g. Can the efficiency of this solution be improved? Explain.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q92: A work cell is scheduled to build
Q128: Why do work cells increase the use
Q131: What are the two basic types of
Q141: A company is designing a product layout
Q143: A firm is planning to set up
Q143: An assembly line with 11 tasks is
Q146: Brandon's computer shop has hired a consultant
Q151: A work cell is required to make
Q254: Explain how a load-distance model helps solve
Q267: What are the advantages of focused factories?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents