Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost. 
A) B; $2,000
B) B; $8,000
C) C; $1,000
D) C; $2,000
E) C; $6,000
Correct Answer:
Verified
Q62: Which of the following statements regarding time-cost
Q62: An activity on a PERT network has
Q63: A project whose critical path has an
Q67: An activity on a PERT network has
Q76: A project being analyzed by PERT has
Q78: If an activity whose normal duration is
Q79: An activity on a PERT network has
Q80: Which of these statements regarding time-cost tradeoffs
Q97: Contract requirements state that a project must
Q125: A network has been crashed to the