A partially solved PERT problem is detailed in the table below. Times are given in weeks.
a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?
e. What is the probability of completion of the project after week 40?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q66: What are the earliest activity start time
Q107: How is the expected completion time of
Q108: Consider the network pictured below.
a. Enumerate all
Q109: A network consists of the following list.
Q110: Consider the network described in the table
Q112: A network consists of the activities in
Q114: Given the project within the table below
Q115: Draw the AOA and AON networks for
Q116: Three critical path activities are candidates for
Q117: The network below represents a project being
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents