Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
a. What is the crash cost per unit time for each of the three activities?
b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q27: Describe some of the challenges faced in
Q35: What is a project organization?
Q40: Describe the differences between a Gantt chart
Q50: The _ is the computed longest time
Q58: What is the basic difference between PERT
Q101: The network below represents a project being
Q104: Briefly describe the concept of cost/time trade-off
Q114: Describe in words how to calculate a
Q115: Briefly discuss what is meant by critical
Q119: What are the advantages of using PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents