The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are
A) 115
B) 175
C) 240
D) 690
E) 700