Lead Time for One of Montegut Manufacturing's Fastest Moving Products

Question 120

Essay

Lead time for one of Montegut Manufacturing's fastest moving products is 4 days. Demand during this period averages 100 units per day. What would be an appropriate reorder point?

Correct Answer:

verifed

Verified

Reorder point = dema...