The annual demand for a product has been projected at 2,000 units.This demand is assumed to be constant throughout the year.The ordering cost is $20 per order, and the holding cost is 20 percent of the purchase cost.The purchase cost is $40 per unit.There are 250 working days per year.Currently, the company is ordering 500 units each time an order is placed.Assuming the company uses a safety stock of 20 units resulting in a reorder point of 60 units, what is the expected lead-time for delivery?
A) 4 days
B) 5 days
C) 6 days
D) 7 days
Correct Answer:
Verified
Q42: Which of the following does not have
Q43: Daniel has computed the EOQ for a
Q44: The demand during the lead-time is normally
Q45: For the basic EOQ model, which of
Q46: The objective of a(n)_ system is to
Q48: Which of the following is not an
Q49: Andre Candess manages an office supply store.One
Q50: The annual demand for a product has
Q51: Andre Candess manages an office supply store.One
Q52: Sensitivity analysis of EOQ refers to
A)the attitude
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents