Subcomponent J has a one week lead time and a gross requirement of 57 units in Week 6 to fill order 123.There are already 15 J's in stock at the beginning of the planning period and these are not needed for any other order other than 123.What should be the planned order release for J's in order to build product at the latest possible completion time?
A) 42 units in week 5
B) 42 units in week 6
C) 57 units in week 5
D) 57 units in week 6
Correct Answer:
Verified
Q108: Everett Mann's Dream Store sells waterbeds and
Q109: David and Beth Sheba run a health
Q110: East Valve Distributors distributes industrial valves and
Q111: Which of the following uses of inventory
Q112: Vicky Payne sells beauty supplies.Her annual demand
Q114: Suppose that lead-time demand is normally distributed
Q115: Furniture Manufacturers Inc.uses 20,000 loads of lumber
Q116: Subcomponent J has a one week lead
Q117: Subcomponent J has a one week lead
Q118: Consider the material structure tree for item
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents