The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks.The construction company must pay a penalty if the project is not finished by the due date in the contract.If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
A) 81.28
B) 92.8
C) 81.82
D) .81954
Correct Answer:
Verified
Q93: The number of calls received by call
Q94: What is the probability that F is
Q95: The time required to travel downtown at
Q96: The number of cell phone minutes used
Q97: What is the F value associated with
Q99: Data for a particular subdivision near downtown
Q100: The time required to complete a project
Q101: Disco Fever is randomly found in one
Q102: Disco Fever is randomly found in one
Q103: Disco Fever is randomly found in one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents