Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
Correct Answer:
Verified
Q74: Given an activity's optimistic, most likely, and
Q75: The project described by: Q76: Table 11-4 Q77: In PERT analysis, the probability of the Q78: Given an activity's optimistic, most likely, and Q80: Table 11-4 Q81: Which of the following is not a Q82: An alternative approach to project crashing is Q83: Reducing the overall activity time is based Q84: Table 11-5![]()