In a PERT network,the earliest (activity) start time is the
A) earliest time that an activity can be finished without delaying the entire project.
B) latest time that an activity can be started without delaying the entire project.
C) earliest time that an activity can start without violation of precedence requirements.
D) latest time that an activity can be finished without delaying the entire project.
E) None of the above
Correct Answer:
Verified
Q1: One PERT/COST assumption is that money is
Q3: In CPM, crashing an activity that is
Q27: The value of work completed is computed
Q32: The activity crash cost is equal to
Q32: Shortening a project is called crashing.
Q34: In PERT,the variance in completion time is
Q38: Slack is the time an activity can
Q39: CPM stands for Comprehensive Project Method.
Q40: The variance of the project completion time
Q41: Given an activity's optimistic,most likely,and pessimistic time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents