Given an activity's optimistic,most likely,and pessimistic time estimates of 2,10,and 20 days respectively,compute the PERT variance for this activity.
A) 3
B) 6
C) 9
D) 18
E) None of the above
Correct Answer:
Verified
Q41: Given an activity's optimistic,most likely,and pessimistic time
Q42: Given an activity's optimistic,most likely,and pessimistic time
Q43: The expected time in PERT is
A)a weighted
Q44: PERT
A)assumes that we do not know ahead
Q45: Slack time in a network is the
A)amount
Q47: Given the following small project,the critical path
Q48: According to Table 11-1,compute the slack time
Q49: Managers use the network analysis of PERT
Q50: Given an activity's optimistic,most likely,and pessimistic time
Q51: Given an activity's optimistic,most likely,and pessimistic time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents