Given the following small project, the critical path is ________ days. 
A) 4
B) 10
C) 12
D) 22
E) None of the above
Correct Answer:
Verified
Q41: Given an activity's optimistic,most likely,and pessimistic time
Q42: Table 12-1
The following represents a project with
Q45: Table 12-2
The following represents a project with
Q46: Table 12-2
The following represents a project with
Q48: Table 12-1
The following represents a project with
Q50: Given an activity's optimistic,most likely,and pessimistic time
Q51: Given an activity's optimistic,most likely,and pessimistic time
Q51: Table 12-1
The following represents a project with
Q57: Given an activity's optimistic,most likely,and pessimistic time
Q60: CPM
A)assumes we do not know ahead of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents