Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?
A) 108.0
B) 110.4
C) 89.6
D) 85.0
E) 100
Correct Answer:
Verified
Q60: CPM
A)assumes we do not know ahead of
Q61: Consider a project that has an expected
Q62: Table 11-2
The following represents a project with
Q63: Table 11-3 Q64: The critical path of a network is