In PERT analysis,the probability of the optimistic time occurring should be on the order of
A) 1/2.
B) 1/3.
C) 1/6.
D) 1/10.
E) 1/100.
Correct Answer:
Verified
Q73: Given an activity's optimistic,most likely,and pessimistic time
Q74: PERT stands for
A)probabilistic evaluation and review technique.
B)program
Q75: Which of the following questions can be
Q76: The work breakdown structure involves identifying the
Q77: Table 11-3 Q79: The expected time in PERT is Q80: Given an activity's optimistic,most likely,and pessimistic time Q81: Given an activity's optimistic,most likely,and pessimistic time Q82: Table 11-5 Q83: The project described by: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents
A)greater than