Given an activity's optimistic,most likely,and pessimistic time estimates of 3,7,and 11 days respectively,compute the expected time for this activity.
A) 5
B) 6
C) 7
D) 12
E) None of the above
Correct Answer:
Verified
Q75: Which of the following questions can be
Q76: The work breakdown structure involves identifying the
Q77: Table 11-3 Q78: In PERT analysis,the probability of the optimistic Q79: The expected time in PERT is Q81: Given an activity's optimistic,most likely,and pessimistic time Q82: Table 11-5 Q83: The project described by: Q84: Given an activity's optimistic,most likely,and pessimistic time Q85: Table 11-4 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents