Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 13 days respectively,compute the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
E) None of the above
Correct Answer:
Verified
Q68: CPM stands for
A)critical path management.
B)critical project management.
C)critical
Q69: The two common techniques for drawing PERT
Q70: In a PERT network,the latest (activity)start time
Q71: In PERT,we assume that
A)the times to complete
Q72: Table 11-2
The following represents a project with
Q74: PERT stands for
A)probabilistic evaluation and review technique.
B)program
Q75: Which of the following questions can be
Q76: The work breakdown structure involves identifying the
Q77: Table 11-3 Q78: In PERT analysis,the probability of the optimistic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents