Given an activity's optimistic,most likely,and pessimistic time estimates of 1,9,and 23 days respectively,compute the PERT expected activity time for this activity.
A) 10
B) 12
C) 9
D) 11
E) None of the above
Correct Answer:
Verified
Q79: The expected time in PERT is
A)greater than
Q80: Given an activity's optimistic,most likely,and pessimistic time
Q81: Given an activity's optimistic,most likely,and pessimistic time
Q82: Table 11-5 Q83: The project described by: Q85: Table 11-4 Q86: Table 11-4 Q87: Table 11-4 Q88: The project described by: Q89: Figure 11-1 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents