Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,6,and 9 days respectively,compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
E) None of the above
Correct Answer:
Verified
Related Questions
Q76: The work breakdown structure involves identifying the
Q77: Table 11-3 Q78: In PERT analysis,the probability of the optimistic Q79: The expected time in PERT is Q80: Given an activity's optimistic,most likely,and pessimistic time Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents