Multiple Choice
Figure 12-1
-Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project?
A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above
Correct Answer: