Which of the following statement about project crashing is false?
A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.
Correct Answer:
Verified
Q101: Consider the project with the following estimates
Q103: Draw the PERT network associated with the
Q104: Development of a new deluxe version of
Q105: Consider the tasks, durations, and predecessor relationships
Q105: Which of the following is not a
Q108: A small software development project has four
Q111: The process of smoothing out the utilization
Q111: Given (Time in weeks): Q113: The crash time of an activity represents Q135: In a PERT analysis, how is the
A)the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents