The annual demand for a product has been projected at 2,000 units.This demand is assumed to be constant throughout the year.The ordering cost is $20 per order,and the holding cost is 20 percent of the purchase cost.Currently,the purchase cost is $40 per unit.There are 250 working days per year.Whenever an order is placed,it is known that the entire order will arrive on a truck in 6 days.Currently,the company is ordering 500 units each time an order is placed.What is the total holding cost for the year using this policy?
A) $400
B) $2,000
C) $4,000
D) $8,000
E) None of the above
Correct Answer:
Verified
Q29: We can usually determine an appropriate safety
Q41: Which of the following does not have
Q42: A structure tree of the components in
Q43: For the basic EOQ model,which of the
Q44: Sensitivity analysis of EOQ refers to
A)the attitude
Q46: What shows how many units are needed
Q47: The objective of a(n)_ system is to
Q48: The EOQ model without the instantaneous receipt
Q49: Judith Thompson is the manager of the
Q50: With _,inventory arrives just before it is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents