Which of the following is not an example of a risk?
A) technology advances make the technology planned obsolete before project completion.
B) non-availability of resources with the needed skills.
C) encountering a large amount of rock while digging the foundation for a construction project.
D) have signs made to give additional directions to attendees.
Correct Answer:
Verified
Q57: A good forum for regularly reviewing, updating,
Q58: The trigger point in the risk response
Q59: _ risk involves determining the likelihood that
Q60: A realistic approach to managing risk is
Q61: Risk response planning involves all the following
Q63: A possible action trigger for rain or
Q64: The possible response plan for vendor delay
Q65: A risk is
A) an uncertain event that,
Q66: The possible impact for rain or snow
Q67: When assigning responsibility for a risk, it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents