If three activities are using the same resource, the network diagram must be draw
A) to show the three activities so that none is a predecessor of the others.
B) to show the three activities performed at the same time.
C) to show the activity sequence with technical constraints only
D) to show a serial relationship for the activities.
Correct Answer:
Verified
Q35: Resource constraints are represented in the network
Q36: Resource requirements graphs based on an as-soon-as-possible
Q37: Technical constraints for a project are represented
Q38: Resource utilization charts based on each activity's
Q39: Activities in a network diagram are drawn
Q40: Which of the following is likely not
Q42: When performing resource-limited scheduling, those activities with
Q43: If three workers are assigned to a
Q44: If not enough resources are available for
Q45: A project is resource leveled without resource-limited
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents