It is a good practice to have the person who will be responsible for performing activities in a project estimate the duration for other activities to be completed by other resources although the person might not have experience with those activities.
Correct Answer:
Verified
Q10: Each organization or subcontractor responsible for a
Q11: If the total slack is zero, the
Q12: This longest path in the overall network
Q13: The estimated activity resources will also be
Q14: Playing the game of inflating estimated durations
Q16: The estimated duration for an activity must
Q17: The sponsor or customer often states the
Q18: The estimated duration should be aggressive and
Q19: The latest finish time for a specific
Q20: For large projects that involve several hundred