Free slack of an activity is
A) the slack on activities that do not have any costs associated with them.
B) can be calculated on every activity with a serial relationship to its successors.
C) the amount of time an activity can be postponed and not delay the start of its immediately succeeding activities.
D) is always a negative value.
Correct Answer:
Verified
Q101: The latest start time for a specific
Q102: If the total slack for a project
Q103: The amount of _ should determine the
Q104: The _ is the estimated cost to
Q105: The latest finish time of a specific
Q107: When planning the project, it is important
Q108: The _ trade-off methodology is used to
Q109: At the beginning of a longer-term project,
Q110: The _ time is the shortest estimated
Q111: The critical path of a project
A) cannot
Unlock this Answer For Free Now!