The WBS should be decomposed to a level that identifies individual work packages for
A) each person that planned the project.
B) each resource assigned to the project.
C) the level of detail specified by the customer.
D) each specific deliverable listed in the project scope document.
Correct Answer:
Verified
Q88: _ is a structured approach for organizing
Q89: The project scope document defines _ in
Q90: To help assure quality, the project quality
Q91: A _ emphasizes who is responsible for
Q92: The _ all of the lowest-level work
Q94: The project team or contractor must avoid
Q95: Having other project team members participate in
Q96: The _ states the specific deliverable that
Q97: Many projects _ because of scope creep
Q98: Quality standards that will be used should