The length of the estimated duration of an activity
A) should last as long as the project.
B) is divided by the number of resources assigned to the task.
C) is dependent upon the time required for the predecessor activity.
D) should not be longer than the review of the actual project progress.
Correct Answer:
Verified
Q156: Quality of the project deliverables should be
A)
Q157: Scope creep
A) is acceptable because the informal
Q158: _ separate(s)the planning and scheduling functions.
A) Gantt
Q159: One of the major drawbacks to the
Q160: The project scope document contains
A) many of
Q161: Deliverables are
A) only listed as the major
Q162: Laddering tasks in a network diagram means
A)
Q163: The lowest levels to include in a
Q164: If two people are assigned primary responsibility
Q166: The quality standards for the project should
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents