____ Outlines the Circumstances Under Which the Contractor Must Notify

Question 125

Multiple Choice

____ outlines the circumstances under which the contractor must notify the customer immediately of any actual or anticipated schedule delays.


A) Misrepresentation of costs
B) Notice of cost or schedule overruns
C) Approval of subcontractor
D) Terms of payment

Correct Answer: