The annual demand for a product is 1,000 units.The company orders 200 units each time an order is placed.The lead-time is 6 days,and the company has determined that 20 units should be held as a safety stock.There are 250 working days per year.What is the reorder point?
A) 20
B) 24
C) 44
D) 120
E) None of the above
Correct Answer:
Verified
Q69: Rolf Steps is the production manager for
Q70: Consider the material structure tree for item
Q71: The demand during the lead-time is normally
Q72: Judith Thompson,the manager of the student center
Q73: The "point at which to reorder" depends
Q75: The annual demand for a product is
Q76: Andre Candess manages an office supply store.One
Q77: As the service level increases,
A)safety stock increases
Q78: Consider the material structure tree for item
Q79: A person is using the normal distribution
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents