The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks.
(a)What is the probability that the project is finished in 40 weeks or fewer?
(b)What is the probability that the project is finished in 52 weeks or fewer?
(c)There is a 95 percent chance that the project will be finished in fewer than how many weeks?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q117: Data for a particular subdivision near downtown
Q118: The Department of Motor Vehicles (DMV)can service
Q119: Data for a particular subdivision near downtown
Q120: The time required to travel downtown at
Q121: In a given office, the color printer
Q122: Compute the F value based on the
Q123: The Department of Motor Vehicles (DMV)can service
Q124: The Department of Motor Vehicles (DMV)can service
Q126: Drivers arrive at a toll booth at
Q131: A new television program was viewed by
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents