Solved

Table 11-2 The Following Represents a Project with Four Activities.All Times Are

Question 67

Multiple Choice

Table 11-2
The following represents a project with four activities.All times are in weeks. Table 11-2 The following represents a project with four activities.All times are in weeks.   -According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )  A) 0.07 B) 0.93 C) 0.43 D) 0.77 E) None of the above
-According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )


A) 0.07
B) 0.93
C) 0.43
D) 0.77
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents