Activity B of a project has a budgeted cost of $50,000 and is 30% complete.The actual cost of the activity is $12,000.What is the activity difference?
A) -15,000
B) -3,000
C) 0
D) 3,000
E) 15,000
Correct Answer:
Verified
Q97: The project described by: Q98: Table 11-4 Q99: Table 11-6 Q100: Consider a project that has an expected Q101: Figure 11-1 Q103: Consider the following project schedule: Q104: PERT often assumes that time estimates follow Q105: Which of the following is not a Q106: Figure 11-1 Q107: PERT/Cost allows a manager to do which Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents