Which of the following statements about project crashing is false?
A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.
Correct Answer:
Verified
Q109: Consider the project with the following estimates
Q110: The value of work completed for an
Q111: The process of smoothing out the utilization
Q112: PERT assumes that the total completion time
Q113: The crash time of an activity represents
A)the
Q115: Figure 11-1 Q116: Consider the tasks,durations,and predecessor relationships in the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents