If the supplier perceives a buyer-supplier relationship is in the desirable region on the purchaser-supplier satisfaction matrix,but there are problems,the supplier is most likely to:
A) insist on unreasonable length of contract.
B) refuse to send shipments as promised.
C) be willing and able to make rapid price,delivery,and quality adjustments in response to requests from the purchaser.
D) insist on unreasonable length of contract and refusal to send shipments as promised.
E) insist on unreasonable length of contract,refusal to send shipments as promised and willingness and ability to make rapid price,delivery,and quality adjustments in response to requests from the purchaser.
Correct Answer:
Verified
Q13: A goal of supply chain management is
Q14: Monitoring changes in market trends and technologies
Q15: There may be legitimate reasons for not
Q16: Trends in supply management include:
A)switching suppliers frequently
Q17: Taking negative measures to shift the satisfaction
Q19: On the purchasing-supplier satisfaction model,if the perceptions
Q20: The supplier evaluation process that includes: (1)factors
Q21: Unilateral price increase without notice is an
Q22: Buyer-supplier relationships fall somewhere on a continuum
Q23: Evaluation and rating systems that assign values
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents