Use the following information to answer questions 13 - 15
The following data is on two one period capital projects.
-What is the variance of each project's cash flow?
A) A = 25,500, B = 9,700
B) A = 50,100. B = 19,400
C) A = 75,200, B = 29,100
D) A = 100,200, B = 38,800
E) A = 125,400, B = 48,500
Correct Answer: