Based on the activity network pictured, what is the best statement? 
A) Activity C is a burst activity.
B) Activity E has one predecessor, Activity B.
C) Activity A and Activity C are merge activities.
D) There are no serial activities in this network.
Correct Answer:
Verified
Q24: Concurrent activities are:
A)activities that must be done
Q32: Serial activities are those that:
A)flow from one
Q33: The amount of time an activity may
Q34: These can be located by doing a
Q35: The least amount of float is found:
A)in
Q36: Prior to creating a network,it is important
Q36: What is the earliest that Activity D
Q37: Based on the activity network pictured, what
Q37: A sequence of activities defined by the
Q43: Ray's shipment of materials hit every red