Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity) . Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration, so activity C in the original project becomes two activities, C1 and C2, each of which last 7 days. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is difference in the late start time for activity C in the original project and activity C1 in the laddered project? 
A) 3
B) 5
C) 7
D) 9
Correct Answer:
Verified
Q56: What is the underlying theory to the
Q75: Activities C, D, and E in the
Q76: Project Test Bank is composed of activities
Q79: A project has the precedence requirements and
Q83: In order to reduce the length of
Q84: The best candidate activities for shortening the
Q87: In general,the better candidates for shortening are:
A)early
Q88: A project's duration can be reduced by:
A)shortening
Q89: Hammock activities allow:
A)project managers to streamline the
Q92: Summaries for some subsets of the activities
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents