When asked to provide an estimate of an irrigation system,Pete looked from one end of the field to the other,licked a finger and held it in the air,squinted into the sun and said $25,000,give or take 30%.The technique employed for cost estimation is:
A) parametric.
B) comparative.
C) definitive.
D) ballpark.
Correct Answer:
Verified