The Consequences of Failure Categories of Cost,schedule,reliability,and Performance Were Believed
The consequences of failure categories of cost,schedule,reliability,and performance were believed to be 0.2,0.6,0.5,and 0.7.What is the overall consequence of failure?
A) 0.2
B) 0.3
C) 0.4
D) 0.5
Correct Answer:
Verified
Q73: What is the relationship between a project's
Q74: The firm set aside a little extra
Q75: With a maturity risk of 0.3,a complexity
Q76: The project team toiled long into the
Q77: It was well known that the cost
Q78: Use the failure probability and consequence scores
Q80: Twenty-thousand dollars was budgeted for the office
Q81: The first phase of a comprehensive project
Q82: A typical risk management report form does
Q86: The tasks of reviewing and refining the