It was well known that the cost of failure category for cost was a 0.7,and for schedule was a 0.8.The project team settled on the cost of failure for reliability of 0.6,and for performance of 0.4.What is the overall consequence of failure?
A) less than or equal to 0.5
B) greater than 0.5 but less than or equal to 0.6
C) greater than 0.6 but less than or equal to 0.7
D) greater than 0.7
Correct Answer:
Verified
Q73: Use the failure probability and consequence scores
Q74: The firm set aside a little extra
Q75: With a maturity risk of 0.3,a complexity
Q76: The project team toiled long into the
Q77: The expected cost of an item that
Q78: Use the failure probability and consequence scores
Q79: The consequences of failure categories of cost,schedule,reliability,and
Q80: Twenty-thousand dollars was budgeted for the office
Q81: The first phase of a comprehensive project
Q82: A typical risk management report form does
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents