In the Analytical Approach,if More Than One Critical Path Exists

Question 62

Multiple Choice

In the analytical approach,if more than one critical path exists in a project management model,the path with the ________ is used.


A) largest expected activity time
B) smallest expected project completion time
C) smallest variance of activity time
D) largest variance of the distribution

Correct Answer: