A project team attempting to close a project should review which of the following to ensure the customers are satisfied that all required work was accomplished?
A) the project charter
B) the customer feedback and scope verification
C) the communication plan
D) the project organization chart
Correct Answer:
Verified
Q1: On long projects it is often better
Q13: A method for documenting and sharing lessons
Q17: Project close-out checklists provide the project manager
Q18: Celebrations of success ease the stress of
Q21: All of the following describe benefits associated
Q24: Identify three factors that might require a
Q25: Describe the approach you would take to
Q25: Many organizations require the completion of a
Q26: All of the following practices have proven
Q28: Project closing can have a significant impact
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents