Question 22

Multiple Choice

Hadley Homes,a building contractor and Wesley have a contract,which calls for Hadley to build a 4-bedroom house with the completion of it by June 15.If the house is not completed by that date,the contract calls for Hadley to pay $100 per day in damages.The $100 per day is:


A) punitive damages.
B) nominal damages.
C) liquidated damages.
D) an illegal penalty.