Activity float is the difference between the late finish and early finish for the activity in question.
Correct Answer:
Verified
Q79: Q80: Use the information in the table Q81: A project has the precedence requirements Q82: A gentleman farmer maniacally works on Q83: Use the values in the table Q85: One approach to reducing project length would Q86: The PERT technique assumes that durations are Q87: Float is always measured in exactly the Q88: Negative float exists when a project's critical Q89: The BEST candidate activities for shortening the