What is the late start time for Activity B given the activity times and precedence requirements shown in the table?
A) 18
B) 9
C) 13
D) 5
Correct Answer:
Verified
Q50: Network logic suggests that: Q51: An activity has an optimistic time estimate Q52: Which of these statements about this network Q53: What is the late finish time for Q54: Based on the activity network pictured,what is Q56: What is the earliest that Activity D Q57: An activity has an optimistic time estimate Q58: Activity Z has estimates a = 5,b Q59: What is the early start time for Q60: What is the early finish time for