Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?
A) 34
B) 38
C) 42
D) 48
Correct Answer:
Verified
Q56: What is the earliest that Activity D
Q57: An activity has an optimistic time estimate
Q58: Activity Z has estimates a = 5,b
Q59: What is the early start time for
Q60: What is the early finish time for
Q62: Use the network diagram and activity lengths
Q63: Use the network diagram and activity lengths
Q64: Project Test Bank is composed of activities
Q65: Use the network diagram and activity lengths
Q66: Use the network diagram and activity lengths
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents